Cleanroom at Biopharmaceutical Company Celltechna

Location

Vilnius, Lithuania

Category

Construction

Size

3000 m²

Clients

UAB Biotecha, UAB Celltechna

Year

2024

The main task was to design and install internal electrical systems in a highly controlled environment that maintains extremely low levels of airborne particles, microorganisms, and contaminants, ensuring sterile conditions for the production of sensitive products.


Challenges

The cleanroom installation presented unique challenges. Due to limited space for engineering systems, a significant amount of time was spent coordinating processes with other contractors.

Our approach

We prioritized efficient planning, close coordination with other contractors, and precise execution to meet strict cleanroom requirements.

Results

The project was successfully delivered with fully integrated electrical systems that support sterile operations in a tightly controlled cleanroom environment.

Overview

Design and installation of internal electrical systems, including the preparation of technical documentation.